§ 16-36A.010. Application review  


Latest version.
  • (a)

    Priority Application Review : A development that will meet the on-site affordability requirement shall be entitled to an expedited administrative review of the BeltLine special administrative permit ("SAP"). The SAP will be given priority and be reviewed within 21 days of submitting a completed application and all Beltline Design Review Committee comments must be given to the City of Atlanta Office of Zoning and Development within 14 days.

    (b)

    Major Projects Meeting : A development that will meet the on-site affordability requirement shall be given major project status and will be afforded a "Major Projects Meeting" in which representatives from all departments that will review the development for permitting will meet with the applicant to identify potential issues and articulate expectations and requirements for permitting.

( Ord. No. 2017-72(17-O-1542), § 1(Exh. A), 11-29-17 )