§ 104.3. PERMITS REQUIRED UNDER THIS CODE AND FEE SCHEDULES.  


Latest version.
  • The following equipment or systems are required to be permitted in accordance with this Code, and Table I, Permit Inspection Fee Schedule.

    (a)

    Any person obtaining a permit shall pay to the City of Atlanta fees in accordance with Table I, City of Atlanta Electrical Division/Schedule of Permit Fees.

    [Table I not available for printing. See Director, Bureau of Buildings]

    (b)

    Any person obtaining a permit shall pay to the City of Atlanta fees as follows:

    1.

    Temporary Pole, each ..... $50.00

    2.

    Disconnect or reconnect of service ..... 50.00

    3.

    Public Utility ..... 50.00

    4.

    Change of Contractor ..... 50.00

    5.

    Service/Disconnects:

    1—200 amps, each ..... 10.00

    201—800 amps, each ..... 20.00

    801—1,200 amps, each ..... 60.00

    1,201—2,000 amps, each ..... 100.00

    2,001—4,000 amps, each ..... 200.00

    Over 4,000 amps, each ..... 300.00

    6.

    Feeders:

    1—30 amps, each ..... 3.00

    31—100 amps, each ..... 5.00

    101—200 amps, each ..... 10.00

    201—800 amps, each ..... 20.00

    801—1,200 amps, each ..... 60.00

    1,201—2,000 amps, each ..... 100.00

    2,001—4,000 amps, each ..... 200.00

    Over 4,000 amps, each ..... 300.00

    7.

    Branch Circuits:

    1—30 amps, each ..... 3.00

    31—100 amps, each ..... 5.00

    101—200 amps, each ..... 10.00

    201—800 amps, each ..... 20.00

    801—1,200 amps, each ..... 60.00

    1,201—2,000 amps, each ..... 100.00

    2,001—4,000 amps, each ..... 200.00

    Over 4,000 amps, each ..... 300.00

    8.

    Low Voltage, per 1,000 sq. ft. ..... 15.00

    (c)

    A reinspection fee of $50.00 shall be imposed for each reinspection after the initial inspection when a written notice has been issued requiring a correction of inferior work.

    (d)

    In the event that any work under this code for which a permit is required is started without a permit first being obtained, the permit fee will be doubled for that permit. However, in no event shall the penalty portion of said fee exceed $1,000.00. In addition, if any work is found to have been performed which is not listed on an existing permit, the cost of adding that work to the permit shall be double the usual fee. However, in no instance shall the penalty portion of that fee exceed $1,000.00.

(Ord. No. 1998-9, § 2, 2-16-98; Ord. No. 2002-11, § 2, 3-5-02; Ord. No. 2002-35, § 2, 5-28-02)